Ukraine, Kherson,
str. Rabochaya 82 a
+38 (050) 396 28 88
+38 (067) 552 64 77
Questionnaire

Maked commissioning of dredges HCC 1200 on the Ordzhonikidze Mining Plant

Maked commissioning of dredges HCC 1200 on the Ordzhonikidze Mining Plant
09.09.2015

In late August, experts VVV-SPETSTECHNIKA conducted commissioning of dredgers HCC 1200 F-E, made to work on the Ordzhonikidze mine. 

Two dredger will take sludge directly from the sludge storage PSCs. Raised  with cutter of dredgers, using pumps, sludge will be served by a system of flexible pipes in the dam, and after that on the pipeline will go straight to the site. Thus, the raw material for the site do not need to use excavators and road transport, as it is to have to do on the UMC-1. Processed sludge to be discharged into the tailings third card PSCs. This waste plant will be immediately involved in the production and combine to give the necessary volumes of concentrate.

Dredger HCC 1200 F E 

Завод ВВВ Спецтехника, Украина
Для просмотра сайта, обновите версию вашего браузера!